M.Y. Yaakun

65m Cantilerri

Refit Period: June 2007 to September 2007

20 year Lloyds survey inspection and repairs; galley systems refit; design and install of new walk in fridge freezer; full hull paint with new colour on the Titan Marine Slipway in 8 weeks; interiors furnishing and decor refresh in master guest and saloon spaces; MTU main engine 20 year survey; rebuild MTU generators; steering systems; stabilizers; new fresh water systems; purifier overhauls; tank cleaning and reconfiguration to suit new installed Hamann system; air conditioning systems maintenance; two custom made wine cellars in saloon; new bar unit fitted to saloon; overhaul & repaint deck cranes; teak decking works; new deck lockers; crew cabin refurbishment; upper deck paint repairs.

Exterior

Re-fair and paint topsides new colour, repaint selected areas of superstructures, repaint all cranes. Lay new teak on all guest areas, build teak storage boxes. Design and build new crew access from foredeck to bridge deck.

Interior

Fit new bar, wine cellars and rebuild all lounge units in saloon, remodel all owner and guest cabins, paint metallic finish on all cabin painted surfaces, build classroom for guests children, overhaul all crew cabins (12) and replace all furnishings to designer specifications. Bridge deck cabinet modifications and chart storages

Engineering

20 year Lloyds special survey, MTU W6 overhaul, generator full rebuild, switchboard rebuild, build and fit new walk in fridge /freezer units with full refrigeration and control system, fit Hamman unit into new cofferdam space, full rebuild of galley with new equipment and work areas and fitted though hull side. Modify and service ship ventilation and HVAC systems. Design and build refrigeration system for two wine cellars to class certification. Rebuild and paint windlasses and all deck cranes. Modify large sections of fuel, ballast and bilge systems. Overhaul pumps, valves and overboard discharges for 20 year survey. Tail shaft and steering system survey. Remove and replace section of hull to allow removal and fitting of new galley and freezer equipment. Modify alarm and monitoring systems. Fit new bridge electronics. Overhaul tenders.